Lack of Progress

Here is the non-detailed to-do list revamp Aljo by Skyline Model 1991:
I'm updating it with any progress... unfortunately there hasn't been much... My dad is supposed to come over tomorrow to do some of the bigger projects... we shall see =)
  1. -buy tarp (18 foot)
  2. -roof sealant and caulking
  3. -remove shelf above bed
  4. -remove vanity, leave shelf?
  5. -replace bathroom vent cover
  6. -remove carpet and install hardwood floors (last)
  7. -paint walls over wallpaper(color?)
  8. -paint wood (color?) ****have decided not to do this****
  9. -paint cabinets (color?)
  10. -paint/cover fridge and oven (color?)
  11. -window treatments (fabric?)
  12. -sink hardware
  13. -shower curtain
  14. -kitchen table: move brackets on current table (color?) or replace tabletop (find replacement)
  15. -replace mattress (measure main bed)
  16. -replace broken back window
  17. -install kitchen backsplash
  18. -replace bathroom vent
  19. -replace bathroom floor
  20. -paint bathroom shower
  21. -replace wood in bathroom
  22. -paint propane tank cover
  23. -5 windows with valances need covered
  24. -10 drawers need painted (color?)
  25. -10 drawers need hardware replaced (brass or copper)
  26. -replace screen in door with lace (red?)
  27. -tile ceiling (color)
  28. -clean vent cover in kitchen
  29. -cover countertop
  30. -power wash exterior
  31. -outside bullet hole fill with calking before painting 
  32. -paint exterior (burgundy, navy blue, cream?)
  33. -repair back cover, screw, spacer and paint
  34. -work in molding around window frames
  35. -rug or astroturf for patio-patio/awning lights
  36. -grind back bumper and paint
  37. -bigger bolts or repair wood for awning 
  38. -stereo work, either replace or hook up to dock
Man, after looking at all the things left to-do I'm feeling overwhelmed again! I forgot I had so many projects!!! Oh well, I will get them done. I JUST KNOW IT! =)

Tuesday, July 5, 2016

The work begins...


LONG TIME, NO SEE!
Before the update I must announce that I have officially named my glamper... drum roll, please *********************************************************************************
GERTRUDE

So I decided the first thing after cleaning would be painting the interior of the camper. I quickly found out that task sounded much simpler than it was in reality. Therefore, I decided I would stick to painting the faces of doors and cabinets as well as the walls... discarding the creative direction that I would in fact paint EVERY SURFACE of the camper.... If I decide I want to take on that task I can do so in the future.

So, with the help of my lovely friend Mel I was able to get the cabinets and doors painted. I chose an antique look (which is hard to see in the pics below) and I must say I really like it!

The renovation is moving VERY SLOWWWWWW but hey, small steps in the right direction.

Here are the finished cabinets/drawers/doors. Next up, painting the wall!!!







Friday, May 27, 2016

Team Meeting

On Saturday 5/21/16 I had another meeting with my team leader, Beard, aka Bill Kelley, aka Dad lol
We simply revisited the to-do list and made a more concrete plan for the GLAMPING process.

We have planned to seal the roof and start on the floor next Saturday... wish us luck! I will keep you posted!